2 creating an »engineer« project & going online, Creating an »engineer« project & going online, 3commissioning – Lenze 8400 TopLine User Manual
Page 70
3
Commissioning
3.8
Commissioning of the "Table positioning" technology application
70
Lenze · 8400 TopLine · Reference manual · DMS 6.0 EN · 06/2014 · TD05/TD14
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
3.8.2
Creating an »Engineer« project & going online
The following steps serve to describe a general method for creating a project with the Select
component from catalogue option. For this purpose, individual components (controller, motor, etc.)
are selected from selection lists.
1. Start the »Engineer«.
2. Create a new project with the Start-up wizard and the Select component from catalogue option:
• In the Component step, select the 8400 TopLine controller.
• In the Device modules step, select the available communication module.
• In the Application step, select the "Table positioning" application. (The application can also
be selected any time afterwards via the Application parameter tab or
• Select the other components (motor/gearbox) to be added to the project in the Other
components dialog step.
3.
Go online.
After a connection to the controller has been established, the following status is displayed in the
Status line:
4.
Transfer parameter set to the device.
This command serves to overwrite the current parameter settings in the controller by
parameter settings of the »Engineer« project.
You can find detailed information on the general use of the »Engineer« in the online help
which you can call with [F1].
• The chapter "Working with projects" describes, among other things, all options of the
Start-up wizard which are available to create a new »Engineer« project.