Commissioning
3.7
Commissioning of the "Actuating drive speed" technology application
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
3.7
Commissioning of the "Actuating drive speed" technology application
[3-1]
Block diagram for wiring the commissioning example for the "Actuating drive speed" application
Commissioning steps
Find a description of the commissioning steps of the "Actuating drive speed" technology application
below.
Please observe the sequence of the steps in the following chapters and follow them through
carefully. This will help you to commission your controller quickly and as safely as possible:
Prepare controller for commissioning
Creating an »Engineer« project & going online
Parameterising the motor control
Saving parameter settings safe against mains failure
Enable controller and test application
Note!
Take all the necessary safety precautions before you carry out the following
commissioning steps and switch the device on!
Safety instructions with regard to commissioning
System constellation
X50/AR
Reference voltage (10 V) for analog signals
X50/A1U
Speed setpoint selection (slider of setpoint potentiometer R)
• Scaling: 10 V ≡ 100 % ≡ 1500 rpm
1
(for a 4-pole motor)
X50/GA
Ground potential (GND) for analog signals
X70
Diagnostic interface for connecting the USB diagnostic adapter
8400 protec
X61
X6
DIAG
AR A1U GA
X50
24O DI1 DI2 GIO
X41
24O DI3 DI4 GIO
X42
24O DI5 DI6 GIO
X43
U
V W
X70
M
3~
i
R
1k
... 10k
W
W