PLC functionality
4.2
Preparations for creating a PLC program
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
4.2.4
Configuring tasks
In the Resources tab in the Task configuration object, the task features of the four tasks described in
the section
Standard project "PLC_Application.pro"
Please make sure that the interval times of the cyclic tasks are limited to the permissible or optional
values.
Tip!
When the checkbox Update unused I/Os (tab Resources Object Target system settings
tab General) is active, a system task with priority 9 is created.
If you have created your own task with priority 9, this will cause the translation error 3570
(error message: "The tasks 'InputUpdateTask' and 'IdleTask' have the same priority 9").
4.2.4.1
Inserting other user tasks
As described in section
Standard project "PLC_Application.pro"
, the Application, User, Visu and Idle
Task exist after creating a new project.
In order to create other user tasks, mark a task and then select the menu command InsertInsert
task.
Task
Priority
Type
Interval time and watchdog time
Sensitivity
Application task
1
cyclic
T = 1 ms
optional: 2 ms, 4 ms or 8 ms,
recommended: 1 ms or 2 ms
1
User task
2
cyclic
T = 2 ms
optional: 2 ms, 4 ms or 8 ms *)
1
Visu task
7
cyclic
Interval time T = 8 ms,
optional also larger
1
Idle task
8
free-running
*) The value of interval times of cyclic tasks must always be selected as the power of two (e.g. 2