4 Introduction to the operation

746 VA Trace Analyzer / 747 VA Stand

4-2

4.1

Preparations

In order to be able to perform the illustrative methods described in section 4.2 ff,

you must first put the 746 VA Trace Analyzer and 747 VA Stand into operation in a

proper manner. Proceed as described in section 4.1.1 and section 4.1.2 (you will

find information regarding the installation in the specified subsections of section 3).

Additional preparations required involve several instrument settings for the 746 VA

Trace Analyzer (section 4.1.3) and various tests for checking the 747 VA Stand

(section 4.1.4).

4.1.1

Installation of the 746 VA Trace Analyzer

When putting the 746 VA Trace Analyzer into operation for the first time, please pro-

ceed in the following sequence:

1

Setting up the instrument

Section 3.1

2

Setting the mains voltage

Section 3.2.1

3

Checking the fuses

Section 3.2.2

4

Mains connection

Section 3.2.3

5

Inserting paper

Section 3.2.5

4.1.2

Installation of the 747 VA Stand

When putting the 747 VA Stand into operation for the first time, please proceed in

the following sequence:

1

Setting up the instrument

Section 3.1

2

Attachment to 746 VA Trace Analyzer

Section 3.3.1

3

Inserting dummy stoppers

Section 3.3.2

Inserting dummy stoppers in measuring head

4

Assembling stirrer

Section 3.8

Assembling stirrer and inserting in measuring head

5

Filling reference electrode

Section 3.5

Filling reference electrode with internal and bridging

electrolyte and screwing together

Internal electrolyte: KCl 3 mol/L (6.2308.020)
Bridging electrolyte: KCl 3 mol/L (6.2308.020)