Page 128: Run subwindow, Run - general, Run test, Performing a run test
3.6 Run subwindow
■■■■■■■■■■■■■■■■■■■■■■
116
■■■■■■■■
viva 1.1 (for process analysis)
3.6
Run subwindow
3.6.1
Run - General
Subwindow: Workplace
▶ Run
Run subwindow
The Run subwindow contains the controls for controlling method runs
and for administering sample data. It is always displayed in the Work-
place program part, i.e., it cannot be removed from the workplace view.
The subwindow can be enlarged and reduced as required; it can also be
maximized.
Tabs
The Run subwindow consists of the following three tabs:
■
Single determination
Control of single determinations.
■
Determination series
Control of determination series.
NOTE
If a run has been started on the Single determination tab (Status =
BUSY), then the Determination series tab is no longer accessible
(disabled). The same holds true for the Single determination tab in
the event that a run has started on the Determination series tab.
3.6.2
Run test
Dialog window: Workplace
▶ Single determination ▶ Tools ▶ Run test ▶ Run test -
'Workplace name' - Single determination
Dialog window: Workplace
▶ Determination series ▶ Tools ▶ Run test ▶ Run test -
'Workplace name' - Determination series
NOTE
As opposed to the Sample table test, which checks only whether all
sample data is correct, the Run test also checks the required hardware.
Single determination
With the Tools
▶ Run test menu item or the symbol, the start test is
carried out for the selected method. The workplace must have the status
READY for this.