background image

4. Commissioning

4−39

Festo P.BE−SPC200−EN en 0901d

Step 6:

Enter test program

In order to avoid unnecessary fault messages during the
switch−on phase, programs 0 and 1 have already been
created at the factory. They each contain the NC record N000
with the command M30 (Program end).

N000

M30

Select therefore the command MODIFY PROGRAM, if you
wish to use program number 0 or 1 for your test program.

Enter a short test program, e.g.:

N000

G02...

X+100

FX50

N001

G02...

X+150

FX90

N002

M30

Adapt the position specifications (X+100, X+150) to your
requirements.

Notes on the procedure for programming with the control
panel can be found in section 6.3.

Step 7:

Test the program

With the command SINGLE STEP in the menu TEST/DIAG.,
you can test saved programs in single steps in the operating
mode START/STOP (see section 6.8).

This operating mode is set at the factory.

Set the operating mode START/STOP as follows:

1. Select the command OPERATING MODE in the menu

CONFIG. SYSTEM.

CONFIG. SYSTEM

OPERATING MODE >