4. Commissioning

4−23

Festo P.BE−SPC200−EN en 0901d

4.4

Commissioning with the control panel

If you wish to use the control panel for commissioning, you
should first be familiar with the functions of the control
panel. Leave the compressed air supply switched off. An overĆ
view of the menu system on the control panel can be found in
section 6.1.1.

The functionality of the MMI (control panel) has been frozen
to that of operating system version 3.8. This means that all
new functions of operating system versions 4.63 and 4.82
can no longer be displayed or edited using the MMI.

Please note
From operating system 4.63 onwards it is recommended to
carry out configuration and commissioning of the SPC200
with the latest version of WinPISA. Only the latest version
of WinPISA provides you with simple and comprehensive
support and the use of all features of the SPC200.

For commissioning with the control panel, proceed as
described in sections 4.4.1 and 4.4.2.

Warning
If the tubing of the axis system is incorrectly connected
and you enable the controller, the drive will move, dependĆ
ing on the level of the supply pressure, at high speed and
with high acceleration into one of the end positions (conĆ
trol direction reversed).
This can lead to serious injury to human beings and
damage to components.

Always check the tubing before enabling the controller
with a 1−signal at the ENABLE input.

Non−compatible
as from

OS 4.63