beautypg.com

Festo Кабели и принадлежности User Manual

Page 152

background image

4. Commissioning

4−8

Festo P.BE−SPC200−EN en 0901d

4.2

Connecting a single−axis system for the first commissioning

Caution

·

Leave the compressed air supply switched off.

·

The SPC200 is set at the factory to certain axis and
application data. Before applying compressed air, you
must adapt these settings to your application and to the
axes which you are using.

You can thereby avoid:

ć

unexpected movements of the connected actuators.

With some commissioning steps, the control signals ENABLE,
START and STOP are required for controlling the axes.

If a field bus module is installed

WinPISA provides a test mode. In the test mode you can
manipulate the inputs and outputs as desired, without these
being connected to the circuitry.

The status of the READY output and the ACK outputs used by
the system (ACK_A, ACK_B, only in the Record Select mode)
are permanently updated by the operating system and canĆ
not therefore be influenced.