beautypg.com

Step 10 – Rockwell Automation Energy Management Accelerator Toolkit Quick Start User Manual

Page 379

background image

Rockwell Automation Publication IASIMP-QS016C-EN-P - October 2014

379

Demand Control Chapter 12

5.

Click on the load number to launch the numeric keypad.

6.

Enter the load number you wish to configure, and then
click Return.

7.

Configure the load priority, rated kW, description, on
delay, off delay, and max off times for the load.

Place the load in Normal Demand Control mode
(Remove OVR if OVR is applied).

8.

To change the mode, click on the mode indicator to
toggle between modes.

9.

Repeat the above step for each load in your application.

10.

Once the demand controller has been configured, enable
the IO mapping routine.

Go online with your RSLogix project and monitor the
Enable_IO tag. Set the tag value to ‘1’ if it is not already
set.