A. Notes on commissioning and service
A−29
Festo P.BE−CPX−CMA X−CONTROL−EN en 0908NH
Operating voltage = 0 V
Load voltage (valve) = 0 V
CMAX is OFF
SCON.MC = 0
SCON.24VL = 0
The output data should in any case be specified
at the beginning to prevent control signals from
the last operating phase from affecting the
CMAX.
Error:
CMAX not reporting back
Reset PLC output
data
Switching on the
operating voltage
Start timer:
3 seconds
The CMAX initialises the axis string and the
controller and queries the setting for the file
format in the CPX node.
Monitoring to detect a faulty module. Time may
vary, depending on the CPXC node.
[m]
[m]
[m]
[m]
[o]
[o]
Timer expired
Timer still running
SCON.FAULT = 0
SCON.FAULT = 1
SCON.MC = 1
Check commissioning
status
Cancel
Error handling
Switch on pressure
Set operating mode
Switch on valve load
voltage (= 24 V)
SCON.FAULT = 0
SCON.FAULT = 1
SCON.24VL = 1
Page
2
Cancel
Error handling
[m]
[m]
[m]
[m]
[m]
[o]
The supply pressure should be fully built up at the valve within 50 msec.
Otherwise allow for additional time after this step, or parametrise E50 as
a warning.
This action is mandatory.
This action is a recommendation. It
does not have to be carried out
[m]
[o]