beautypg.com

A.1 preparations and overview for commissioning, A.1.1 checking the axis string, Preparations and overview for commissioning – Festo Контроллер позиционирования CPX-CMAX User Manual

Page 311: A.1.1, Checking the axis string, A.1.2, Switching on the power supply, switch−on behaviour

background image

A. Notes on commissioning and service

A−3

Festo P.BE−CPX−CMA X−CONTROL−EN en 0908NH

A.1

Preparations and overview for commissioning

A.1.1

Checking the axis string

Prior to commissioning:

·

Check the complete system structure, especially the drive
tubing and the electrical installation (see CMAX system
description).

A.1.2

Switching on the power supply, switch−on behaviour

Warning
High acceleration forces at the connected actuators! UnexĆ
pected motion can cause collisions and severe injuries.

·

Switching on:
Always first switch on the power supply and then the
compressed air supply.

·

Switching off:
Before carrying out mounting, installation and maintenĆ
ance work switch off the power supply and the comĆ
pressed air supply, either simultaneously or in the folĆ
lowing sequence:
1. the compressed air supply
2. the power supply for the electronics/sensors
3. the load voltage supply for the outputs/valves
Always make sure that the compressed air supply and
power supply are switched off and locked before workĆ
ing in the machine area.