A. Notes on commissioning and service
A−3
Festo P.BE−CPX−CMA X−CONTROL−EN en 0908NH
A.1
Preparations and overview for commissioning
A.1.1
Checking the axis string
Prior to commissioning:
·
Check the complete system structure, especially the drive
tubing and the electrical installation (see CMAX system
description).
A.1.2
Switching on the power supply, switch−on behaviour
Warning
High acceleration forces at the connected actuators! UnexĆ
pected motion can cause collisions and severe injuries.
·
Switching on:
Always first switch on the power supply and then the
compressed air supply.
·
Switching off:
Before carrying out mounting, installation and maintenĆ
ance work switch off the power supply and the comĆ
pressed air supply, either simultaneously or in the folĆ
lowing sequence:
1. the compressed air supply
2. the power supply for the electronics/sensors
3. the load voltage supply for the outputs/valves
Always make sure that the compressed air supply and
power supply are switched off and locked before workĆ
ing in the machine area.