Figure 69 jumper connections – Nortel Networks 1000M User Manual
Page 153

NTAK76 battery unit installation
153
DANGER
DANGER OF ELECTRIC SHOCK
The battery cells can deliver high currents when
short-circuited. Make sure that you do not inadvertently
short-circuit the terminals of the batteries.
5
Unpack the batteries and check the expiry dates. If the batteries do
not have the same dates, contact your supplier.
6
Place the batteries in the battery unit with the terminal end down.
Hold the batteries in place with the restraining bar.
7
Locate the three white jumper wires and the red and black jumper
cables supplied with the NTAK76 battery unit.
8
Connect the battery packs in series by connecting the white jumper
wires between the + (red) terminal of one battery pack to the -
(black) terminal of the next battery pack. (See
Figure 69
Jumper connections
9
Connect the remaining red and black jumper cable to red and black
terminals of the first and fourth battery pack.
10
Connect the jumper cable to the NTAK76 breaker panel, marked J1.
Nortel Communication Server 1000
Communication Server 1000M and Meridian 1 Small System Installation and Commissioning
NN43011-310
01.04
Standard
Release 5.0
13 May 2008
Copyright © 2008, Nortel Networks
.