Hardware installation, Summary of installation procedure, Pre-installation steps – Grass Valley Maestro Master Control Installation v.2.4.0 User Manual
Page 105: Section 3 — hardware installation
MAESTRO — Installation and Service Manual
105
Section
3
Hardware Installation
This section is intended for studio engineers who are actually installing the
standard Maestro system. That is, a system without the Channel Branding
and Dual Channel DVE options. The Installation steps for these options can
be found later on in this manual; Channel Branding Hardware Installation
, Dual-Channel DVE Hardware Installation
System integrators or others who are developing a system plan should
refer to the Installation Planning section of this manual.
Summary of Installation Procedure
The following is a summary of the steps needed for installation of the
Maestro Master Control Switcher. Additional details may be found else-
where in this manual as indicated.
Pre-Installation Steps
Follow these steps before installing the standard Maestro system:
1.
Inspect the shipping carton for evidence of freight damage before
unpacking the system. Carefully unpack and inspect all equipment for
freight damage.
If the contents have been damaged, notify the carrier and Grass Valley.
Retain all shipping cartons and padding material for inspection by the
carrier.
Do not return damaged merchandise to Grass Valley until an appro-
priate claim has been filed with the carrier and a Material Return
Authorization number has been received from Grass Valley.
2.
Verify the installation and operation of the external matrix router (for
example, Trinix or Concerto) and control system (for example, Encore
or Jupiter) that is associated with the Maestro system.
3.
Check the line voltage settings as follows:
- Concerto Routing Matrix v.1.7.6.1 Concerto Routing Matrix v.1.8.1 Concerto Routing Matrix v.1.7.5 Kayenne Installation v.4.0 Kayenne Installation v.3.0 Kayenne K-Frame Installation v.6.0 Kayenne K-Frame Installation v.7.0 Kayenne K-Frame Installation v.8.0 Karrera K-Frame S-Series Installation v.8.0 Karrera Video Production Center Installation v.6.0 Karrera Video Production Center Installation v.7.0 Karrera Video Production Center Installation v.4.1 Karrera Video Production Center Installation v.4.0 7600REF v5.0 7600REF v3.0.0.8 7600REF v5.0 Installation 7600REF v3.0.0.8 Installation 7620PX-5 Installation 2012 7620PX Installation 2012 KayenneKayenne v.2.0 v.2.0 Maestro Master Control Installation v.2.3.0 Maestro Master Control Installation v.2.0.0 Maestro Master Control v.2.3.0 7620PX 2012 7620PX-5 2012 7620PX 2008 MVMC 3G VMCR 3G 8900F GeckoFlex Frames Concerto Compact Routing System GPIO-4848 Jupiter Maestro Master Control v.2.2.0 Maestro Master Control v.2.0.0 Maestro Master Control v.2.4.0 Maestro Master Control Installation v.2.2.0 Maestro Master Control Installation v.1.5.1 Maestro Master Control Installation v.1.7