Synchronizing server databases on redundant server, Confirming databases are synchronized – Rockwell Automation 1757-SWKIT4000 ProcessLogix R400.0 Installation and Upgrade Guide User Manual
Page 147

Publication 1757-IN040B-EN-P - March 2002
Additional Redundant Server Procedures 6-13
Synchronizing Server Databases on Redundant Server
1. On SERVERA, click Start
⇒
Programs
⇒
ProcessLogix
Server
⇒
Station.
2. Click View
⇒
System Status
⇒
Server Redundancy to call up the
Server redundancy display.
3. Click the Oper field in the lower right corner of the display.
4. Key in >mngr< in the Station Logon dialog box and press
5. Click Synchronize. When the Synchronize Databases (Y/N)
prompt appears, key in >Y< in the entry field above the display
and press
6. Wait for the synchronization to complete (“Synchronization
Complete” prompt appears) and verify that the display shows
simulated Green LED indications for the following states:
Primary Server
•
Running
Backup Server
•
Synchronized
•
Running
Link Status
•
Link 0 (LNK00) - OK Active link
•
Link 1 (LNK01) - OK Active link (Only applies if you are
using a dual LAN)
7. Click Station
⇒
Exit.
8. Click Yes to exit Station.
9. Verify redundancy has been established on both SERVERA and
SERVERB by using for DOS command C:\dual_status.
Confirming Databases are Synchronized
1. On SERVERA, click
Start
⇒
Run.