Replacement Procedures

5–41

11. Install a new I/O module.

12. Connect the cables (there may be one or two) to the I/O module.

13. Press return to resume device port activity. When all port activity has

restarted, FRUTIL displays the following:

I/O module replacement complete.

In a dual-redundant configuration, FRUTIL also displays:

The configuration has two controllers.

To restart the other controller:

1. Type ’restart other_controller’.

2. Press and hold the reset button while inserting the

program card on the slot A [or B] controller, then

release the reset button.

The controller will restart.

Field Replacement Utility terminated.

14. To allow the “other controller” to restart, type the following command:

RESTART OTHER _CONTROLLER

15. Hold the reset button while inserting the program card into the new

controller. Release the reset button and replace the ESD cover. The
controller will restart.

16. Enable failover and re-establish the dual-redundant configuration with

the following command:

SET FAILOVER COPY=THIS_CONTROLLER

This command copies the subsystem’s configuration from “this
controller” to the “other controller.”

17. Disconnect the PC or terminal from the controller’s maintenance port.