Subwindow Run
123
6 - Main run
When processing the loaded method the following actions can be carried out:
• Process series start track
At the start of the first determination in a series the Series start track is
started. If during the run of this track
[Stop]
is pressed then the Exit
track will start; if an error occurs the Error track starts.
• Process main track
After the start of the Main track the status changes to
BUSY
. The com-
mands of the main track and the other tracks that it calls up are proc-
essed in sequence. If the main track calls up tracks that are not free
then a pause will be made until these tracks can be started.
• Interrupt and continue run
A running determination can be interrupted at any time with
[Hold]
and
then continued with
[Cont]
. All the active tracks will be stopped and
continued together.
• Interrupt and continue series
A running series can be interrupted at any time with
[Pause]
. The de-
termination that is running in the series will be completed, but no new
determination will be started. With
[Cont]
the next determination in the
interrupted sample series will be started.
• Cancel sequence
A running determination can be canceled at any time with
[Stop]
. An
Exit track may be carried out; the determination will be terminated.
• Cancel by error
If when a determination is being carried out an error occurs that
causes the cancellation of the determination then an Error track may
be carried out; the determination will be terminated.
• Process exit track
When the main track and all the other tracks that is has called up have
been completed then an Exit track may be carried out; the determina-
tion will be terminated.
• Process series end track
At the end of the last determination in a series the Series end track will
start. If when this track is being processed
[Stop]
is pressed then the
determination will be terminated, if an error occurs then the Error track
starts.
7 - Post-conditioning (only for methods with conditioning)
In methods that contain commands with switched-on conditioning and in which
the option
Automatic conditioning
is switched on in the
START
command then for all
these commands post-conditioning will be started automatically with the loaded
method immediately after the end of the track that contains the conditioning
command. After the start of post-conditioning the status changes to
COND BUSY
.
In this status the conditioning can be stopped with
[Stop]
or interrupted with
[Hold]
and continued with
[Cont]
. If an error occurs during conditioning then neither the
Error track nor the Exit track will be carried out.
• Conditioning between two determinations
Conditioning will continue to run until the new method is loaded for the
next determination.
• Conditioning at the end of the last determination
After the Series end track has been carried out conditioning will con-
tinue to take place until it is terminated with
[Stop]
.