beautypg.com

Lenze E94ARNE Regenerative power supply User Manual

Page 17

background image

EDS94ARNExxxx EN 2.3 - 06/2014

L

17

9400 regenerative power supply module | Parameter setting

Commissioning

Short setup

7. Carry out optional parameter setting:

Parameterising the brake chopper/brake resistor

( 22)

Signal configuration

( 30)

• Establish network/communication.

8. Switch on 24-V supply of the regenerative power supply module.

• With the first switch-on of the regenerative power supply module, the filter

data are automatically read out of the electronic filter nameplate (ENP) and

temporarily saved in the regenerative power supply module.

9. Click the icon.

10. Confirm the following note with Yes to accept the changes on the project:

The Build project dialog box is displayed:

11. Click Build to build the project.

• After the project has been built successfully, a corresponding note is displayed.