1 prepare controller for commissioning, Prepare controller for commissioning, 3commissioning – Lenze 8400 HighLine User Manual
Page 82
3
Commissioning
3.9
Commissioning of the "Switch-off positioning" technology application
82
Lenze · 8400 HighLine · Referenzhandbuch · DMS 10.0 EN · 06/2014 · TD05/TD14
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
3.9.1
Prepare controller for commissioning
1. Power terminal wiring.
Refer to the mounting instructions supplied with the drive controller to find help on how to
correctly design the power connections to match the requirements of your device.
2. Control terminal wiring.
In case of the application shown in illustration
[3-3]
, switch-off positioning without pre-switch
off, wiring according to the "
" control mode makes sense:
3. Inhibit controller: Set terminal X5/RFR to LOW level or open contact.
4. Connect USB diagnostic adapter.
5. Switch on voltage supply of the controller.
• Without motor operation: Connect external 24 V supply.
• With motor operation: Connect mains voltage.
If the green "DRV-RDY" LED is blinking and the red "DRV-ERR" LED is off, the controller is ready for
operation and commissioning can proceed.
Related topics:
Automatic restart after mains connection/fault...
DI3
DI2
DI4
DI5
DI6
DI7
GI
24I
DI1
RFR
24E
+
=
X5
Controller enable / reset error
Stop function 1
Stop function 2
CW rotat. quick stop / selection: switch-off pos. 1
CCW rotat. quick stop / selection: switch-off pos. 2
External 24 V DC
supply