Station manager basics, How to start the station manager application – MTS Series 793 User Manual

Page 117

background image

Item

Callout

HSM - Controls hydraulic service manifolds through Power Off,
Power Low, and Power High buttons.

The names of station power resources originate in the hardware
interface file (.hwi) associated with the station configuration.
You can edit the name of these resources with the Hwi File
Editor application.

Sets the master span for all channels included in a master span
group.

24/25 - Master Span

MPT procedures where the MPT Option Editor window’s Span
control is set to Disable and Reset makes this control
unavailable.

Use the Channel Options window’s Master Span tab to define
master span groups.

The Station Option window’s Display Master Span on Main
Window
control must be selected to display this control. If this
selection is not made, Master Span will be displayed in the
Setpoint and Span window.

Sets the master gain for all station channels. Master gain is a
multiplier of the gains for all the PID control loops in your station.

24/25 - Master Gain (Option)

Station Manager Basics

How to Start the Station Manager Application

Note:

Before you start the Station Manager application, station hydraulic power must be off and any ongoing
test must be stopped. You may also need to shut down some applications connected to the station
before you can open the station.

From the desktop:

Start > Programs > MTS 793 Software > Station Manager

From other MTS applications:

On the Project Manager toolbar, click the Station Manager icon, or from the Applications menu, click
Station Manager.

From the Station Desktop Organizer toolbar, click Start Station Manager.

When you first start the Station Manager application:

The System Loader utility starts and establishes a real-time connection with your hardware components.

MTS Series 793 Control Software 117