Commissioning

Medium Voltage Tests

Pre-Power Tests

Inspect cabinets for debris (tools, hardware, metal shavings, etc.)

Re-install control fuses (to be done with control power off)

Power Tests

Verify that line voltage is at rated value

Perform a phasing check (18 Pulse drives only)

Verify input line harmonic by checking line voltage and current waveforms at ACB board (only for AFE rectifier
drive
); save the waveforms

Perform IDC Test and verify dc current and voltage waveforms

Autotune the drive

Review parameters settings for operating the drive with unloaded motor

Program the drive for operation at full load

Run the drive at rated load and rated speed, and record variables

Capture line side and load side voltage and current waveforms under running condition

Paperwork

Print DRIVE SETUP, which gives all parameters, firmware revisions, PLC links, etc.

Complete the Commissioning Datasheets

Mark up EDs with modifications or corrections done in the control circuit

Add revision notes to modified PLC program

Have the customer sign sign-off documents

Provide customer with parameter settings, marked-up drawings, commissioning package, PLC program and
Field Report

Forward Waveforms, PLC program, modified drawings, Commissioning Package and Field report to Medium
Voltage Support group