Pre-Commissioning
Responsibilities

In order to avoid complications during commissioning, it is important to ensure
that the drive line-up is ready to be commissioned. Included in this chapter is a
seven-point Pre-Commissioning Checklist. It is necessary that the checklist be
reviewed to ensure that all points are completed in the order that they have been
presented prior to beginning the drive commissioning. Completing the items in
the checklist prior to commencing drive commissioning will help to ensure that
the start-up is performed in an organized and efficient manner.

Please print the following information:

PowerFlex 7000 ‘C’ Frame
Pre-Commissioning Checklist

Once all points of the checklist are complete, initial each check box and provide
the date. Photocopy the checklist and fax the copy to Medium Voltage Center of
Expertise (MV COE), along with the planned start-up date. Upon receiving this
checklist, the MV COE will contact the site to finalize arrangements for a start-
up engineer to travel to site if so desired by the end user.

Receiving and Unpacking

Medium Voltage - Center of Expertise
Fax: 1 (866) 465-0103, or 1 (519) 740-4756

Name:

Date:

Company:

Phone:

Pages:

Fax:

Drive Serial Number

CSM Service Engineer Requested (YES/NO)

Scheduled Commissioning Date

Initials

Date

The drives have been checked for shipping damage upon receiving.

After unpacking, the item(s) received are verified against the bill of materials.

Any claims for breakage or damage, whether concealed or obvious, are made to the carrier
by the customer as soon as possible after receipt of shipment.

All packing material, wedges, or braces are removed from the drive.