beautypg.com

5 initial functional tests, Power-on check, Standalone configuration operation check – AMETEK ReFlex User Manual

Page 196

background image

ReFlex Power™

Fixed Power DC Power Supply

M380056-01 Rev J

5-27

5.5.5

I

NITIAL

F

UNCTIONAL

T

ESTS

P

OWER

-O

N

C

HECK

1. Ensure that the AC/DC input service is disconnected.

2. Install the interface cable between the host controller and the ReFlex

Power™ Controller module.

3. Connect an appropriate output load to one or more of the FPDC power

supply module outputs.

4. Configure the host controller for communications with the ReFlex

Power™ Controller module.

5. Turn on the AC/DC input service.

6. The modules will first execute a power-on self-test. Also the internal fans

are run at maximum speed for several seconds, and then back to slow
speed.

7. Verify communications with the ReFlex Power™ Controller module by

issuing an SCPI *IDN?,

8. The ReFlex Power™ Controller module should respond with its

identification string.

9. Verify communications with the ReFlex Power™ FPDC power supply

module by issuing an SCPI *IDN[n]?, where “n” is a channel number
that corresponds to the slot of the ReFlex Power™ Mainframe where the
module is located, counting left to right, 1 through 12.

10. The FPDC power supply module should respond with its identification

string. The default settings of the module will not be affected.

S

TANDALONE

C

ONFIGURATION

O

PERATION

C

HECK

1. Connect the output for standalone operation per the section, Standalone

Configuration.

2. Connect appropriate instrumentation for measuring the output voltage and

current, as well as a load.

3. Perform the power-on verification test per the preceding section, Power-On

Check.

4. Turn on the isolation and remote sense relays

5. Turn on the outputs

6. Measure the output voltage and current with the external instruments.

7. Turn off the output with the following command:

*RST[n]