4.5.5

I

NITIAL

F

UNCTIONAL

T

ESTS

P

OWER

-O

N

C

HECK

Ensure that the AC/DC input service is disconnected.

Install the interface cable between the host controller and the ReFlex

Power™ Controller module.

Connect an appropriate output load to the AC power supply module.

Configure the host controller for communications with the ReFlex Power™

Controller module.

Turn on the AC/DC input service, and the power switch on the ReFlex

Power™ Controller.

The modules will first execute a power-on self-test. Also the internal fans are

run at maximum speed for several seconds, and then back to slow speed.

In the following paragraphs, commands include a channel number, [n]. The

channel number corresponds to the slot of the ReFlex Power™
Mainframe where the module is located, counting left to right, 1 through
12. For example:

SOUR[n]:VOLT 5

will be

SOUR1:VOLT 5

for slot-1

SOUR2:VOLT 5

for slot-2

Additionally, model specific parameter values must be added for full scale

voltage and current. They are shown in the following examples as floating
point numerical values, . For the AC power supply modules, the
values are as follows:

Full-Scale Voltage:

140/280V

RMS

Full-Scale Current:

7/3.5 A

RMS

Therefore, the command for full scale voltage would be:

SOUR1:VOLT 140.

Verify communications with the ReFlex Power™ Controller module by issuing

an SCPI *IDN[n]?, where “n” is a channel number that corresponds to