13B. WCC III - MCD2 INSTALLATION GUIDE
WCC III Technical Guide
13B-5
System Requirements
To accomplish remote communications via the internet, the 
following items are needed in addition to the WCC III system in 
order to control the building mechanical systems:
WARNING:
The WCC III-MCD2 system is not to be used in
any application where Fire/Life/Safety is an issue.
The WCCIII-MCD2 Basic Operating
Conditions
The WCCIII-MCD2 must be kept in a clean and dry area in the 
building. The ambient temperature must be between 50 and 100 
°F, and the relative humidity must be kept between 0 and 90% 
(non-condensing). 
The WCCIII-MCD2 is primarily designed to mount on a wall.
The WCCIII-MCD2 computer requires 115 VAC power and must 
remain powered at all times for proper operation and control. The 
115 VAC power circuit must be separate and dedicated exclusively 
to the WCCIII-MCD2 computer. An APCTM brand UPS with an 
USB connection must also be connected to the to the WCCIII-
MCD2 for backup power.
A dedicated Network IP Address or Domain Name is required.
WCCIII-MCD2 Basic System
Requirements (On-Site WCCIII-MCD2
Computer)
•
DSL or a Cable router/switch that connects to the 
internet. Or, as an alternative, an internal jobsite 
IP network that does not connect to the internet, 
but when using this internal jobsite IP network, the 
external internet Email of alarms from the WCCIII-
MCD2 will not be possible. Also, external access 
via the internet may not be possible. An Ethernet 
crossover cable is supplied for standalone non-
network applications.
•
A fi xed static IP address or a fi xed IP domain host 
name from the ISP along with a provisioning sheet 
that contains other pertinent IP setup information.
•
Enabled port forwarding on the Firewall of the 
router/switch. This is only if a Firewall is used.
•
An Email address that supports a SMTP 
server for SENDING with a pop server for 
RECEIVING Emails, and it must have “authlogin” 
authentication—TLS or SSL modes are supported. 
WattMaster Controls can provide an Email address 
with these requirements.
•
An APC
TM
brand Uninterruptible Power
Supply (UPS) – 700 Watt minimum with USB 
communications.
•
A wall mounting surface is desirable, and preferred.
•
A dedicated 120VAC power circuit is required.
Front End Software Requirements
(Operator Console Software)
•
A Microsoft Windows XP /Vista/Windows 7/ 
Windows 8 -based computer.
•
Minimum hardware specifi cation for the Microsoft 
Windows XP / Vista based computer is a Pentium 
IV running at 2.4 Giga Hertz with at least 1 GB 
of RAM, and 10 GB of spare hard drive space. A 
CDROM/DVD drive is also required for software 
installation.
•
WCC III software package – Provided on a 
CDROM (WattMaster Part # DM1WC011-01X, 
were “X” = revision level), or is available via a 
download on the WCC Controls website: www.
wcc-controls.com. The installation CDROM 
contains the following programs:
 
WCC III.exe (SS5021)
WCCUTILITY.exe (SS5023)
SCUSCR.exe (SS5026)
WCC3Trendlog.exe (SS5028)
TenantReport.exe (SS5025)
TenantOverride.exe*(SS5024)
WCC3Download.exe (SS5030)
WCC3Guest.exe (SS5022)
*NOTE:
The TenantOverride.exe program is also
available as a single program installation for the 
end users that are using the simplistic graphical 
interface of the TenantOverride.exe screen to 
locally turn on and off specifi c control points that 
are applicable to the end user.
•
A DSL or Cable router/switch that connects to the 
internet, or access to the internet via some other 
method. Or, as an alternative, an internal jobsite IP 
network that does not connect to the internet, but 
when using this internal jobsite IP network, the 
external internet Email of alarms from the WCCIII-
MCD2 may not be possible.