Point slope staking - screen 3 – Spectra Precision Survey Pro v5.0 User Manual
Page 153
HR: is the rod height.
[Topo SS…]: will store the last shot taken as a side shot.
[Shot]: takes a shot.
Point Slope Staking – Screen 3
The third Point Slope Staking screen is identical to the fifth Slope Staking screen.
Stake Line and Offset
[Stakeout] [Line and Offset]
The Stake Line and Offset screen is used to stake stations on a line, or at an offset to it, at fixed intervals.
Start Point: defines the first point of the line to be staked.
[End Point] / [Direction]: defines the second point of the line, or the direction of the line to be staked, respectively.
Begin Station: defines the station associated with the Start Point.
[Backsight…]: opens the
[Next>]: opens the
: opens the
Stake Line and Offset – Screen 2
Station to Stake: is the desired station that you want to stake.
Station Interval: is the value that is added to the Station to Stake after the [Next Sta] button is pressed.
[Next Sta]: advances the Station to Stake by the Station Interval.
Offset: defines the offset distance and if the offset occurs to the right of the line, when R is selected, or left, when
L is selected. The right or left side is referenced while viewing the line from the Start Point.
[Vertical Offset]: is the offset distance that is below the design location (when D is selected) or above the design
location (when U is selected).
[> Grade]: specifies a slope from the specified line to the parallel line that is being staked. When this is a non-zero
value, the elevation for the staked points will increasingly differ from the design elevations as the Offset value
increases.
Survey Pro Help 5.00
153