Titration sequence for stat – Metrohm 840 PC Control 5.0 / Touch Control User Manual
Page 234

4.1 Titrations
222
PC Control / Touch Control
The parameters for Control device, Sensor, Dosing device and
Stirrer
are described in the following Section.
Titration sequence for STAT
Start of titration
command
(Switch on stirrer)
The stirrer is switched on after the start.
Measure initial meas-
ured value
The initial measured value is measured.
(Start conditions:
Pause 1
Start volume
Pause 2)
Pause interval 1 is allowed to elapse. The start
volume is added. No measuring points are en-
tered in the list of measuring points. Pause inter-
val 2 is allowed to elapse.
Titration
Titration to the control point is carried out.
During this time controlling is active as well as
monitoring. Measured values are not entered in
the list of measuring points until the titration pa-
rameters (Start time, Start measured value, Start
rate) are fulfilled.
Stop conditions
The first criterion to be fulfilled applies for stop-
ping the titration.
(Switch off stirrer)
The stirrer is switched off.
Fill dosing
cylinder
After the end of the titration the dosing cylinder is
refilled automatically.
Optional steps are shown in brackets.