3 Operating tutorial
732 IC Detector / 733 IC Separation Center
48
3.3
Putting into operation
After the complete IC system has been installed as described in sec-
tion 3.2, it can be put into operation. In what follows, all operating steps
up to the first calibration with the standard solution are described in se-
quence.
Please note that all displays refer to the condition in which the instru-
ment was put into operation for the first time (initial condition). If you do
not run through this tutorial until a later date, differences in regard to the
dialog language and the parameter values can appear. How you return
to the initial condition in such a case is described in section 5.4.9.
In this description of putting the instruments into operation, it is as-
sumed that all instruments are shut down and must first be switched
on. If this is not the case (e.g. if you start the operating tutorial immedi-
ately following the conditioning), you can skip steps 1
1 – 3
3.
1 Switch on external devices
⇒
Switch on recorder (if used).
⇒
Switch on «IC Metrodata for Win95» and PC
(if used).
⇒
Switch on other recording and evaluation system
(if used).
2 Switch on 709 IC Pump
⇒
Switch on 709 IC Pump with mains switch 29
29
(see section 2.6.4 of the 709 Instructions for Use).
3 Switch on remote control for 709 IC Pump
(the pump must be connected to the 732 IC Detector with a
6.2125.060 RS Cable for this)
⇒
Set sliding switch 36
36 at the rear of the 709 IC Pump to
"
RS
232
"
(see Fig. 2 of the 709 Instructions for Use).
⇒
Press key 88
external control (see section 3.6 of the 709 Instructions for
Use).
When the external control is activated, LED 77 above the
exception of the
now possible only via the 732 IC Detector.