Cold Replacement

In cold replacement, none of the replacement work is performed with the
maintenance menu from a terminal connected to XSCF.

The procedure is as follows.

1. Unlock and open a door of the server.

For details, see

Chapter 5

.

2. Change the mode switch setting on the OPNL from the Locked position to the

Service position.

Note –

When the maintenance work is completed, be sure to confirm the mode

switch setting and return the switch to Locked.

3. Stop (turn off power) all domains together. Take either of the following two

actions:

Press and hold the POWER switch on the operator panel for at least four
seconds.

From a console that is connected to XSCF, log in to XSCF, and execute the
poweroff -a

command.

The OS shutdown processing is executed for all the domains, and then the
power-off processing is executed.

4. Confirm that the power-off processing is completed by confirming that the

POWER LED (green) on the PCI card is off.

5. Switch off all main line switches for the AC section (ACS) in the power supply

system.

For details, see

Section 4.5.3, “Main Line Switch Locations” on page 4-28

.

Note –

If the optional three-phase 200 VAC input power supply unit is installed, the

main line switches are located on the three-phase ACS.

Caution –

If the dual power feed option is installed, switch off the main line