4 cold replacement, 1 powering the server off, Cold replacement – FUJITSU SPARC ENTERPRISE M8000 User Manual

Page 112: Powering the server off

background image

4-18

SPARC Enterprise M8000/M9000 Servers Service Manual • August 2009

4.4

Cold Replacement

In cold replacement all business operations are stopped. Cold replacement is the act
of powering off the server and disconnecting input power. This is normally required
for safety when the inside of the server is accessed. The work of cold replacement
consists of the following three steps:

Section 4.4.1, “Powering the Server Off” on page 4-18

Section 4.4.2, “Powering the Server On” on page 4-19

Section 4.4.3, “Confirming the Hardware” on page 4-20

4.4.1

Powering the Server Off

Two power-off procedures are available.

From the Operator Panel

Follow the power-off procedure below.

1. Confirm that the mode switch on the operator panel is set to the Service

position.

2. Confirm that the POWER LED and CHECK LED on the operator panel are lit

and the XSCF LED on the operator panel is off.

3. When the XSCF LED is lit, see

Section 2.7, “LED Error Display” on page 2-30

to

identify the cause and give preference to these functions.

4. Press and hold down the POWER switch on the operator panel for at least four

seconds.

5. Check the POWER LED. When it turns off, the power-off procedure is

completed.

If the state of any of the LEDs is different from the above, see

Section 2.7, “LED

Error Display” on page 2-30

From the Maintenance Terminal

Follow the power-off procedure below using the XSCF maintenance functions.

1. Notify users that the server is going down.