3 cold replacement, Cold replacement – FUJITSU SPARC ENTERPRISE M8000 User Manual
Page 263
Chapter 11
XSCF Unit Replacement 11-11
For the version matching of firmware, see the SPARC Enterprise
M3000/M4000/M5000/M8000/M9000 Servers XSCF User’s Guide.
12. Close the door on the server, and lock it.
11.3
Cold Replacement
In cold replacement, none of the replacement work is performed with the
maintenance menu from a terminal connected to XSCF.
The procedure is as follows.
1. Unlock and open a door of the server.
For details, see
.
2. Change the mode switch setting on the operator panel from Locked to Service.
Note –
When the maintenance work is completed, be sure to confirm the mode
switch setting and return the switch to Locked.
3. Stop (turn off power) all domains together. Take either of the following two
actions:
■
Press and hold down the POWER switch on the operator panel for at least four
seconds.
■
From a console that is connected to XSCF, log in to XSCF, and execute the
poweroff -a
command.
The OS shutdown processing is executed for all the domains, and then the
power-off processing is executed.
4. Confirm that the power-off processing is completed by confirming that the
POWER LED (green) on the operator panel is off.
5. Switch off all main line switches for the AC section (ACS) in the power supply
system.
For details, see
Section 4.5.3, “Main Line Switch Locations” on page 4-28
.
Note –
If the optional three-phase 200 VAC input power supply unit is installed, the
main line switches are located on the three-phase ACS.