beautypg.com

Schneider Electric Processor Adapter User Manual

Page 106

background image

Assembling Momentum Components

106

870 USE 101 10 V.2

Installation Guidelines, Continued

Leave Power On
When Changing
Batteries

Once your CPU has been commissioned and is running, maintain power to the
module whenever you change the batteries.

Unless you save to flash, if you change the batteries while the power is OFF, you
will have to reload your user logic program from the original files.

Removing and
Replacing
Batteries

Battery maintenance should be performed only by qualified personnel according to
the following illustration.

Monitor the
Battery

Because a Momentum CPU assembly is designed to be installed in a cabinet
where it cannot be seen at all times, no LED was created to monitor battery health.

We recommend that you reserve a battery coil in your programming panel software
configuration and use it to monitor the health of your battery and report the need for
replacement prior to battery failure (refer to

Reserving and Monitoring a Battery

Coil on page 224 for Modsoft or Reserving and Monitoring a Battery Coil on page
328 for Concept).