beautypg.com

Time estimations – Rockwell Automation 7000 PowerFlex Medium Voltage AC Drive (B Frame) - ForGe Control (PanelView 550) User Manual

Page 181

background image

Rockwell Automation Publication 7000-UM151E-EN-P - January 2013

181

Component Definition and Maintenance Chapter 3

– A detailed description of ALL ADJUSTMENTS AND

MEASUREMENTS that were taken during the process should be
included in an addendum (Interlock Adjustments, Loose Connections,
Voltage Readings, Megger Results, Parameters, etc.)

Time Estimations

Note: ** indicates that the time may not be required depending on the nature of
the maintenance and the condition of the drive system. These times are only
estimations.

IMPORTANT This information should be communicated to MV product support so that

future support activities will have the latest site information available.
Fax this information to (519) 740-4756.

Operational Maintenance

0.5 hours per filter

Annual Maintenance
Initial Information Gathering

0.5 hours

Physical Checks

Torque Checks

2.0 hours

Inspection

2.0 hours

Cleaning **

2.5 hours **

Meggering

1.5 hours

Control Power Checks

Contactor Adjustments **

2.0 hours **

Voltage Level Checks

1.0 hours

Firing Check

0.5 hours

System Test **

2.0 hours **

Medium Voltage Checks

Final Inspection

0.5 hours

Phasing Check **

1.5 hours **

Autotuning**

2.0 hours **

Operation to Maximum Load

Site Dependent

Additional Tasks

Investigation **

Depends on Nature of the Problem **

Informal Training/Refresher **

2.0 hours **

Spare Parts Analysis **

1.0 hours **

Vacuum Bottle Integrity Check **

3.0 hours **

Final Report

3.0 hours