beautypg.com

Shortcut key 5: enclosure leakage test – Fluke Biomedical 601PRO XL User Manual

Page 63

background image

M A N U A L M O D E

3 - 2 3

SOFT KEY 1

toggles the DUT outlet Polarity from Normal to Off to Reverse.

SOFT KEY 2

toggles the DUT outlet from Earth to No Earth.

SOFT KEY 3

toggles the DUT outlet from L2 to No L2.

SOFT KEY 4

toggles the AP to Earth to No AP to Earth.

• Press the

print data

key at any time to generate a printout of the latest

measurement.

Shortcut Key 5: Enclosure Leakage Test

Run an Enclosure Leakage test on the device being tested before performing any

leakage tests.

Leakage current is measured the following ways:

♦ Enclosure Leakage, leakage current measured from RED input jack to DUT

outlet Earth.

♦ Enclosure Leakage AP-EARTH (ALL Applied Parts connected to Earth),

leakage current measured from RED input jack to DUT outlet Earth.

The following outlet conditions apply when performing this test:

⇒ Normal Polarity, Earth Open, Outlet ON

⇒ Normal Polarity, Outlet ON

⇒ Normal Polarity, L2 Open, Outlet ON

⇒ Reversed Polarity, Outlet ON

⇒ Reversed Polarity, Earth Open, Outlet ON

⇒ Reversed Polarity, L2 Open, Outlet ON

To perform an

Enclosure Leakage

test in a single lead mode:

• From the

MAIN MENU

, or with the outlet unpowered, plug the DUT into the

601PRO front panel outlet, and turn on the device.

• Attach the RED test lead from the 601PRO to the device. A bare exposed metal

area should be selected.

• Attach the device's applied parts to the 601PRO applied part terminals if

applicable.