Link blocks – Pilz PSS SB HYD, Basic license User Manual
Page 234

7-2
Link Blocks
Modular Block System: Hydraulic Presses
These can be optimised during commissioning.
- Enter a minimum scan time.
- If test pulses are to be connected to the 3 ms inputs (E x.16 ... E x.31):
Make sure the DI test time is set correctly.
• Establish the sequence in which the blocks will be called up
- MBS blocks must be run through as part of each cycle.
- Aid: Flow chart and listing.
• Create a supervisory (master) block
- The master block should be either a PB or an FB
(if parameters are required: FB).
- Call up the blocks in the correct sequence and set parameters for them
° Assign a different number to each block SSNR (1 ... 600)
° Document the SSNR you have used
° If necessary, combine the enable output parameters (FG/ENBL) into
suitable groups by means of a logic AND-operation.
- Remember to take into account any links which have already been
made.
- Enter details on the operation of the selected fault indicator
• Import / set up DB015 or DB015/DB016/DB017 in the project
- DB015/DB016/DB017 must always contain 1024 data words
- DB015/DB016/DB017 must have READ/WRITE status
• Create OB120
If necessary, add SB070 or SB071 call.
- PSS SB HYD, General license PSS SB HYD, Copy license PSS SB HYD, Update license PSS SB TRA, Basic License PSS SB TRA, General license PSS SB TRA, Copy license PSS SB TRA, Update license PSS SB NOT, Basic license PSS SB NOT, general license PSS SB NOT, Copy license PSS SB NOT, Update license PSS SB FT, Basic license PSS SB FT, General license PSS SB FT, Copy license