246 Maintaining
Networks
15. Specify the stencils that will be scanned for master SmartShapes during resynchronization. When
objects are found within the OpenLNS network database that are not already represented in the
drawing, OpenLNS CT scans the listed stencils and automatically adds the appropriate
SmartShape to the drawing. If the object’s particular master SmartShape is not found, an
appropriate generic master SmartShape (e.g., a L
ON
W
ORKS
Device SmartShape) will be used.
To add additional stencils, click Add Stencil. To remove a stencil, select the desired stencil and
then click Remove.
16. Click Finish. Resynchronization begins and the Synchronization Status dialog opens.
This dialog displays the status of the resynchronization. Resynchronization events are listed in
order as they occur. Click OK when the resynchronization is complete. The resynchronization