Commissioning
Commissioning examples
Multi−axis application
6.14
6.14.2
l
6.14−4
EDSVS9332K EN 8.0−07/2013
9300std225
Fig. 6.14−4
"Management" menu of the parameter menu
Procedure
1.
Change to the "Management" menu.
2.
Set the node address of the controller under C0350.
l
C0350 = 1: Master
l
C0350 = 2: Slave 1. The address is increased by 1 for every further slave.
3.
Set the baud rate under C0351.
l
The baud rate must be set identically for all controllers. (Recommended: 500 kbps for a
cable length of up to 100 m)
4.
Set CAN master operation under C0352.
l
C0352 = 1: Master
l
C0352 = 0: Slave
5.
Save the settings with C0003 = 1.
6.
When the configuration has been completed, plug in terminal X4 on all controllers.
7.
Execute a ’reset node’ (C0358 = 1) via the master to make the settings effective.
l
Alternatively you can switch off the mains and − if used − the external 24V supply and
then switch the supply(ies) on again.
8.
Click on C0359 and check the bus state.
l
If "Operational" (C0359 = 0) is displayed, all parameters are set correctly.
Basic settings for system bus