Wait action setting, Program initial setting, Program operation parameters – Yokogawa Data Acquisition with PID Control CX2000 User Manual
Page 150: Event setting, Pt sets the segment time, Pu sets the ramp-rate time unit/ ramp, Pg segment pid group number, Pj sets the segment shifting action and wait, Event setting et sets the time event, Wait action setting pz sets the wait zone

6-21
IM 04L31A01-17E
6
Command
PT
Sets the segment time
Syntax
PT p1,p2
p1: Segment number (1 to 99)
p2: Segment time (hh:mm:ss fixed format)
hh
Hour (00 to 99)
mm
Minute (00 to 59)
ss
Second (00 to 59)
Set a value greater than or equal to 1 s.
Query
PT[ p1]?
PU
Sets the ramp-rate time unit/
ramp
Syntax
PU p1,p2,p3
p1: Segment number (1 to 99)
p2: Ramp-rate time unit (Hour, Minute)
p3: Ramp (ramp per unit time 1 digit to EUS
(100%))
Query
PU[ p1]?
PG
Segment PID group number
Syntax
PJ p1,p2
p1: Segment number (1 to 99)
p2: Segment PID group number (1 to 8)
Query
PG[ p1]?
PJ
Sets the segment shifting action
and wait
Syntax
PJ p1,p2,p3,p4
p1: Segment number (1 to 99)
p2: Segment shifting action*
p3: Wait (Off/Shift/Within)
p4: Wait zone number (1 to 5) (selectable only
when p3 is set to Shift or Within)
*:Continue/HoldShift/LocalShift/
ResetShift
Query
PJ[ p1]?
Event Setting
ET
Sets the time event
Syntax
ET p1,p2,p3,p4,p5
p1: Segment number (1 to 99)
p2: Event number (1 to 16)
p3: Enable/disable event (Off, On1, On2, On3)
p4: On-time (hh:mm:ss fixed format)
hh
Hour (00 to 99)
mm
Minute (00 to 59)
ss
Second (00 to 59)
p5: Off-time (hh:mm:ss fixed format)
hh
Hour (00 to 99)
mm
Minute (00 to 59)
ss
Second (00 to 59)
P5>P4
Query
ET[ p1,p3]?
6.4 Setting Commands (Control)
Wait Action Setting
PZ
Sets the wait zone
Syntax
PZ p1,p2,p3,p4,p5
p1: Loop number (1 to 6) (1 or 2 on the CX1000)
p2: Wait zone number (1 to 5)
p3: Wait Off/On
p4: High boundary of the zone (1 digit to EUS
(100.0%))
p5: Low boundary of the zone (1 digit to EUS
(100.0%))
p4 and p5 can be specifed only when p3 is ON.
Query
PZ[ p1,p2]?
PW
Sets the wait time
Syntax
PW p1,p2
p1: Wait zone number (1 to 5).
p2: Wait-time setting (hh:mm:ss fixed format)
hh
Hour (00 to 99)
mm
Minute (00 to 59)
ss
Second (00 to 59)
Query
PW[ p1]?
Program Initial Setting
PO
Sets the start setpoint
Syntax
PO p1,p2
p1: Loop number (1 to 6) (1 or 2 on the CX1000)
p2: Start target setpoint EU (0.0 to 100.0%)
Query
PO[ p1]?
PQ
Sets the start code
Syntax
PQ p1
p1: Start code*
*: StartTargetSP
RampPV1Start
TimePVStart
RampPV2Start
RampPV3Start
RampPV4Start
RampPV5Start
RampPV6Start
Query
PQ?
Program Operation Parameters
PD
Sets the ramp/soak select
Syntax
PD p1,p2
p1: Segment number (1 to 99)
p2: Ramp/soak selection (Ramp/Soak)
Query
PD[ p1]?
PM
Sets the final target setpoint
Syntax
PM p1,p2,p3
p1: Segment number (1 to 99)
p2: Loop number (1 to 6) (1 or 2 on the CX1000)
p3: Final target setpoint EU (0.0 to 100.0%)
Query
PM[ p1,p2]?