HEIDENHAIN iTNC 530

99

3.9

BORE

MILLING

(Cy

cle

208)

3.9 BORE MILLING (Cycle 208)

Cycle run

1

The TNC positions the tool in the spindle axis at rapid traverse FMAX

to the programmed set-up clearance above the workpiece surface

and then moves the tool to the bore hole circumference on a

rounded arc (if enough space is available).

2

The tool mills in a helix from the current position to the first

plunging depth at the programmed feed rate F.

3

When the drilling depth is reached, the TNC once again traverses

a full circle to remove the material remaining after the initial

plunge.

4

The TNC then positions the tool at the center of the hole again.

5

Finally the TNC returns to the set-up clearance at FMAX. If

programmed, the tool moves to the 2nd set-up clearance at FMAX.