Appendix B Installation of B68 Cabinet

B-26

(1) Flat washer Φ12 (2)

Spring

washer

Φ12

(3) Bolt M12%35

(4) Nut M12

(5) Side floor bracket

(6) Angle support of right slide rail

(7) Angle support of left slide rail

(8) Angle plate for floor bracket

(9) Front floor bracket

Figure B-28

Installation of front and side floor brackets

III. Locating the front and side floor brackets

Adjust the locations of the front and side floor brackets in vertical direction so as to
ensure the upper surface of the brackets is at the same height of the lower surface of
the raised floor, then fasten the bolt M12X35.

B.3.6 Cabinet Leveling

I. Moving the cabinet into position

Lift the cabinets on the slide rails one by one and align centers of the cabinet feet with
the centers of the trough on the slide rails. Meanwhile align all cabinets.

Adjusting the cabinets: Place a horizontal ruler in two orthogonal directions on top of
the cabinet to check the cabinet levelness. If the cabinet is not leveled, loosen the
retaining nuts on the cabinet feet with a wrench and turn the cabinet foot finely to adjust
the cabinet height to make it leveled. Meanwhile, align all of the cabinets, and then lock
the retaining nuts on the cabinet feet until they are pressed tightly against the bottom
plane of the cabinet. Figure B-29 shows the cabinet feet fastening