Caution – Yokogawa GC8000 Process Gas Chromatograph User Manual
Page 107

<4. Display and Operations while Connected to GC8000>
4-60
IM 11B06C01-01E
4.5.6
Calling up Re-integration Window from Analysis
Results Window
l
Re-integration from the Concentration Analysis Results window and Retention
Time History window
The Chromatogram Re-integration window can be called from the Analysis Results window by
performing the following operations at user level C+.
(1) While the Concentration Analysis Results window and Retention Time History window
appear, left double-click “Peak concentration” or “Peak retention time” you want to re-
integrate, or select “Re-integration” in the menu at right.
In the Chromatogram Re-integration window started up then, the selected “Peak” has
already been selected as the re-integration target.
(2) While the Concentration Analysis Results window and Retention Time History window
appear, left double-click “Analysis start date and time” including the peak concentration or
retention time you want to re-integrate, or select “Re-integration” in the menu at right.
In the Chromatogram Re-integration window started up then, all peaks in “Analysis start
date and time” have already been selected as the re-integration target.
CAUTION
If the Concentration Analysis Results window and Retention Time History window display GCM,
and the Chromatogram Re-integration window is called from “Analysis start date and time”, the
system select box appears. Select and determined the system number. If only a single target
GCM is in the system, the system select box does not appear.
Figure 4.74
System select box
5th Edition : Nov. 16, 2011-00