To purge the product lines, proceed as follows:

Amount to Purge at Nozzle

Use the following table to determine the amount of fuel that is to be dispensed when purging
the unit through the nozzle. Use an appropriately-sized Prover Can:

For

Pump This Amount

Start-ups (installing new systems)

35* gallons (132.5 liters) per hose

*Applies to the amount purged through the dispenser hydraulics after
purging the underground plumbing of air.

Figure 6-4: Typical Shear Valve and Test Port

Test Port

To purge all air from lines and pumps/dispensers for new installations, proceed as follows

(see

Figure 6-4

):

1

Shut off all power to the STP involved.

2

Start with the unit farthest from the tank and then move to units that are closer to the tank.

3

Use a UL-approved sealant and connect a fuel-resistant hose and petcock valve to the shear
valve test port for dispensers. Leave the valve closed.

4

Place the end of the hose into an approved container.

5

Restore power to the STP. Activate the STP for the line being purged.

6

Open the mechanical valve and purge the product lines slowly, until a steady stream of fuel is
observed.

7

After purging, shut off power to the STPs and remove the line and petcock valve from the