Purging product lines (new installations), Purging product lines (new installations) -10 – Gasboy Atlas Start-up User Manual
Page 130

Page 6-10
MDE-4334D Atlas™ Start-up and Service Manual · July 2013
Hydraulic/Mechanical Components
Purging Air from System
Purging Product Lines (New Installations)
To purge the product lines, proceed as follows:
Amount to Purge at Nozzle
Use the following table to determine the amount of fuel that is to be dispensed when purging
the unit through the nozzle. Use an appropriately-sized Prover Can:
For
Pump This Amount
Start-ups (installing new systems)
35* gallons (132.5 liters) per hose
*Applies to the amount purged through the dispenser hydraulics after
purging the underground plumbing of air.
Figure 6-4: Typical Shear Valve and Test Port
Test Port
To purge all air from lines and pumps/dispensers for new installations, proceed as follows
):
1
Shut off all power to the STP involved.
2
Start with the unit farthest from the tank and then move to units that are closer to the tank.
3
Use a UL-approved sealant and connect a fuel-resistant hose and petcock valve to the shear
valve test port for dispensers. Leave the valve closed.
4
Place the end of the hose into an approved container.
5
Restore power to the STP. Activate the STP for the line being purged.
6
Open the mechanical valve and purge the product lines slowly, until a steady stream of fuel is
observed.
7
After purging, shut off power to the STPs and remove the line and petcock valve from the
shear valve.