Displaying the task function, Displaying the task percent done – HP NetRAID-4M Controller User Manual
Page 291

13-3
Working with Tasks
TaskId Function Done% Container State Specific1 Specific2
------ -------- ------- --------- ----- --------- ---------
103 Create 63.5% 00 RUN 00000000 00000000
Displaying the Task Function
The
task function
attribute indicates the type of task running on
the controller. See the Command Line Interface Reference Guide for a
description of task types. To display the task function of a task
running a controller, use the
task list
command, as in the
following example. In the example, the Function column indicates
that Create is the task function for task 103.
HPN0> task list
Executing: task list
Controller Tasks
TaskId Function Done% Container State Specific1 Specific2
------ -------- ------- --------- ----- --------- ---------
103 Create 63.5% 00 RUN 00000000 00000000
Displaying the Task Percent Done
The
task percent done
attribute indicates the progress
(percentage complete) of a running task. A running task is complete
when the percentage done is 100%. To display the percentage done
for a running task, use the
task list
command, as in the
following example. In the example, the Done% column indicates
63.5%
, which means that the percentage done is 63.5% for task 103.
HPN0> task list
Executing: task list
Controller Tasks
TaskId Function Done% Container State Specific1 Specific2
------ -------- ------- --------- ----- --------- ---------
103 Create 63.5% 00 RUN 00000000 00000000