13.

Apply medium voltage to the drive and perform operational

checks.

14.

Bump motor for rotation check and tune drive to the system

attributes. (If the load is unable to handle any movement in the
reverse direction the load should be uncoupled prior to bumping
the motor for directional testing).

15.

Run the drive motor system throughout the operational range

to verify proper performance.


Please Note: Customer personnel will be required on-site to
participate in the start-up of the system.


Commissioning the Drive


Information contained in this chapter will assist in commissioning
a PowerFlex air-cooled medium voltage AC drive. This chapter
contains reference material with information including:

• Recommended Tools and Equipment

• Safety Checks

• Drive line-up Data Sheets

• Pre-Power Checks

• Control Power Checks


Review the information contained in this chapter prior to
commissioning the drive. It will be used as a reference while the
drive line-up commissioning is performed. Record all the
information requested in the data sheets. The information
recorded on the data sheets will be useful during future
maintenance and troubleshooting exercises.


Perform the commissioning checks illustrated in this chapter in the
sequence that they have been presented. Failure to do so may result
in equipment failure or personal injury.