Level 10 system power-on procedure, Chapter 2 installing the level 10 storage system – Grass Valley K2 Storage System Instruction Manual v.3.3 User Manual
Page 78

78
K2 Storage System Instruction Manual
June 25, 2009
Chapter 2 Installing the Level 10 Storage System
Level 10 system power-on procedure
Power on Level
Level 10 (iSCSI) K2
Storage System
Power on and verify
control point PC
.
for procedures.
Power on and verify
HP ProCurve switch
.
Refer to
for procedures.
Power on and verify
RAID devices
.
for procedures.
Elapsed time: 5 minutes
Elapsed time: 1 minute
Power on the
K2 Media Server
.
From the control point PC, at
the command prompt, ping
the K2 Media Server.
Power on
K2 Media Clients
and other
iSCSI clients
.
Begin record/play operations.
Yes
Power on optional
NH servers
, if any.
From the control point PC, at
the command prompt, ping
the K2 Media Server.
Yes
K2
Media Server
responds to ping?
Elapsed time:
3 minutes
No
K2 Storage System
power-on complete
K2
Media Server
responds to ping?
Elapsed time:
3 minutes
No
Begin FTP operations.