Ku-band odu installation, 2 ku-band odu installation – Comtech EF Data C5 User Manual
Page 107

C5/K1/K3 Integrated Satellite Terminal System
Installation
Rev. 0
3–11
3.3.2.2
Ku-Band ODU Installation
1. Install ODU as follows:
a. Install ring brackets on the ODU and secure to bracket using supplied
hardware.
b. Connect the ODU to the OMT and secure with two U-bolts, four split
washers, and four nuts.
c. Connect the receive cable from the ODU to the IDU CP2 connector.
d. Connect the transmit cable from the ODU to the IDU CP1 connector.
CAUTION
1. The transmit and receive cables may be 300 feet (91 meters) in
length (maximum). Ensure the cables are protected to avoid
shorting, arcing, or damage that would impair its function.
2. Ensure the transmit and receive cables are properly installed.
Improper installation of the cables will cause the LNA to be
damaged.
2. Perform operational testing of the Ku-Band System as outlined in Chapter 6,
System Checkout.