54

K2 Storage System Instruction Manual

September 6, 2006

Chapter 2 Installing the Level 1 Storage System

4. Power-off the control point PC and/or the NetCentral server PC, if necessary.

Level 1 system power-on procedure

Use the following steps to power-on the Level 1 storage system

.

Using FTP for file transfer

Refer to

Chapter 11,

FTP on the K2 Storage System.

Device

Verification instructions

1.

Power-on the control point
PC and/or the NetCentral
server PC.

After log on, start NetCentral. NetCentral reports devices as
offline. As each device is powered on, check NetCentral to verify
the device’s status.

2.

Power-on the Ethernet
switch.

This description is for the HP
ProCurve switch.

The switch performs its diagnostic self test, which takes
approximately 50 seconds to complete. LED Behavior during the
self test is as follows:

Initially, all the status, LED Mode and port LEDs are on
for most of the duration of the test.

Most of the LEDs go off and then may come on again
during phases of the self test. For the duration of the self
test, the Test LED stays on.

When the self test completes successfully, the Power and Fan
Status LEDs remain on, the Fault and Test LEDs go off, and the
port LEDs on the front of the switch go into their normal
operational mode, which is as follows:

If the ports are connected to active network devices, the
LEDs behave according to the LED Mode selected. In the
default view mode (Link), the LEDs should be on.

If the ports are not connected to active network devices,
the LEDs will stay off.

If the LED display is different than what is described above,
especially if the Fault and Test LEDs stay on for more than 60
seconds or they start blinking, the self test has not completed
correctly. Refer to the manual you received with the switch for
troubleshooting information.

3.

Power-on the Level 1 device.

Flip down the front bezel and press the stand-by button.
The Power LED goes on and stays on. The Service LED stays
off.

4.

Power-on K2 Media Clients
and other iSCSI clients.

Record/play operations are successful.

NOTE: K2 Media Clients and iSCSI clients will
not connect (and will have to be restarted) if the
primary K2 Media Server is not fully up and
running when the clients are started.

This manual is related to the following products: