beautypg.com

Level 3 system power-on procedure – Grass Valley K2 Storage System Instruction Manual v.3.1 User Manual

Page 191

background image

September 6, 2006

K2 Storage System Instruction Manual

191

Level 3 system power-on procedure

2.

Power-on the Ethernet
switch.

This description is for the HP
ProCurve switch.

The switch performs its diagnostic self test, which takes
approximately 50 seconds to complete. LED Behavior during the
self test is as follows:

Initially, all the status, LED Mode and port LEDs are on
for most of the duration of the test.

Most of the LEDs go off and then may come on again
during phases of the self test. For the duration of the self
test, the Test LED stays on.

When the self test completes successfully, the Power and Fan
Status LEDs remain on, the Fault and Test LEDs go off, and the
port LEDs on the front of the switch go into their normal
operational mode, which is as follows:

If the ports are connected to active network devices, the
LEDs behave according to the LED Mode selected. In the
default view mode (Link), the LEDs should be on.

If the ports are not connected to active network devices,
the LEDs will stay off.

If the LED display is different than what is described above,
especially if the Fault and Test LEDs stay on for more than 60
seconds or they start blinking, the self test has not completed
correctly. Refer to the manual you received with the switch for
troubleshooting information.

3.

Power-on RAID storage
devices.

Power-on expansion chassis (if present) prior to or simultaneous
with the power-on for the main Fibre Channel chassis.

NOTE: Always power-on the RAID Expansion
chassis prior to, or simultaneously with the
RAID Controller chassis.

Verify that start-up indicators show normal start-up processes, as
follows:

DIR and SVP LEDs on the RAID controllers are blinking
green

Disk Link LED is steady ON green.

FLT and BAT LEDs are OFF.

The front Power LED is ON, Service LED is OFF after
about 5 minutes.

Refer to the

L3 RAID

Instruction Manual to interpret other

disk access LED or status LED behavior.

4.

Power-on the K2 Media
Server that is the media file
system/database server.

Flip down the front bezel and press the stand-by button.
The LCD display lights during normal system operation.
Wait until start up processes are complete before powering up
clients. When the server responds to the ping command, startup
is complete. If you are not sure, wait 10 minutes.

5.

Power-on the remaining K2
Media Server. This is the FTP
server.

Flip down the front bezel and press the stand-by button.
The LCD display lights during normal system operation.
Wait until start up processes are complete before proceeding.
When the server responds to the ping command, startup is
complete. If you are not sure, wait 10 minutes.

Device

Verification instructions

This manual is related to the following products: