2. HDLM Functions

33

Offline operation: Offline operation performed in the Path Management window

or by executing the

dlnkmgr

command's

offline

operation.

#1

During reserve processing for an LU, the Online status is temporarily changed to

Online(P)

. When the reservation processing finishes, the

Online(P)

status is

changed to

Offline(C)

.

#2

When the following conditions are satisfied, the connected

Offline(C)

paths

are automatically placed online:

All the online paths are

Online(E)

and all the SCSI devices connected to

the

Online(E)

paths have been deleted.

SCSI devices are connected and all the

Offline(E)

paths are subject to

automatic failback.

SCSI devices are connected to the

Offline(C)

paths.

#3

When a path is added dynamically, initially the path status is

Offline(C)

. The

path status will then automatically change to

Online

. For details on dynamically

adding a path, see 4.7.1 Setting Up an Added LU and Path as an HDLM

Management-target.

#4

When the following conditions are all satisfied, a path that has been determined

to have an intermittent error also becomes subject to automatic failback:

All the paths connected to an LU are

Online(E)

,

Offline(E)

, or

Offline(C)

.

All the paths connected to an LU have been determined to have an

intermittent error.

The processing of continuous I/O operations issued to an LU is successful.

#5

During reserve processing for an LU, the

Offline(E)

status is temporarily

changed to

Offline(P)

. After the reserve processing finishes, the

Offline(P)

status is changed to

Offline(C)

.

#6

When the following conditions are satisfied, the connected

Offline(E)

paths

are automatically placed online:

All the online paths are

Online(E)

and all the SCSI devices connected to