MDE-4375 CFN Series Site Controller III Start-Up Manual · June 2005

Page 53

Component Power-Up and Configuration

8 – Component Power-Up and Configuration

Turning On AC Power

Turn on the AC POWER for all system devices as follows.

Power Conditioner/AC Surge Protector Strip
Plug in device. Turn on power switch if applicable.

Monitor
Locate the AC power switch on the monitor and turn on. See the operator’s manual for monitor
adjustments and LED indicators.

Logger/Printer
Locate and turn on the AC power switch for the logger/printer. If using a Link terminal for
remote log-in, see the setup parameters later in this section.

CheckPoint or Profit Point
CheckPoint: Locate the AC power switch on the back side of the unit. Push the switch down
to the ON position marked 1. Verify that the console is on by observing the display on the
front of the unit. If the site has an optional customer display, verify that it is also working.
Profit Point: Locate the AC power switch on the front lower righthand side of the monitor and
the AC power switch on the back righthand side of the Profit Point console. Push the switch
for the monitor into the ON position; then do the same for the console. Verify that it powers
up.

Site Controller
Locate the AC power switch on the front of the PC and turn it on. Some units may also have a
power switch in the back.

Verify that the Site Controller is operating properly. Verify that power up message prints on
monitor and/or logger.

Island Card Reader (ICR)
Locate the AC power switch inside the ICR assembly, upper righthand corner and turn it up to
the ON position. Verify that the two power supply LEDs (red) are lit. Verify that the two 485
communication LEDs (red), located on the upper lefthand corner of the reader CPU board, are
flashing.

Pump Control Unit(s)
Locate AC power switch and battery switch and turn them on. Verify that the two power
supply LEDs (red) are lit. Verify that the two RS-485 communication LEDs (red) on the pump
control CPU board are flashing.

Electronic Pumps and Dispensers
Locate and turn on power switches. Refer to the Pump Interface Manual or call Gasboy
Technical Service for information.