14 – finish start-up, Finish start-up – Gasboy Site Controller III Start-Up User Manual
Page 117

MDE-4375 CFN Series Site Controller III Start-Up Manual · June 2005
Page 105
Finish Start-up
14 – Finish Start-up
1
Be sure customer has current backup copies of all SC III release media (CD and disks) and
stored in a safe place. As an ASR, you may wish to make copies for yourself. Also make sure
all disks and CD’s that were supplied with the SC III PC are stored in a safe place.
2
Answer questions and/or demonstrate the optional commands or devices such as: user and
cron commands, disable and enable commands, the diagnostic commands, the system override
switches, and modem polling procedure (including modem phone number, baud rate, and
password).
3
Close and secure all doors for the pump control unit(s) and island card reader(s).
4
Lock out the test cards.
5
Generate a printout showing a few transactions with quantity, pump fuel assignments,
limitation codes, authorization codes, and pulse rates. Use the commands P DA, P TR, P PU,
P A, P LI, P DI, P PR, P PRO, and STATUS. Also generate a printout showing any
configuration changes that were made. Include these printouts with the Start-up form.
11. CUSTOMER KNOWLEDGE
Briefly describe the customer’s understanding of the CFN Series System. Write in the amount of time spent
on training and who was trained.
Check to see that the test cards are locked out (Step 5) and indicate the name of the person with whom the
test cards were left.
Indicate whether backups of the system and any configuration changes were made.
Fill in any remarks you may have regarding the start-up or the system. Use additional sheets if necessary
and staple to form. Be sure to include any configuration changes that you may have done at start-up.
12. ATTACH PRINTOUTS
Generate printouts using the commands noted (Step 5) and attach to the Start-Up Form.
13. PARTS USED
Any defective parts resulting from a start-up should be returned with a completed GASBOY Warranty
Service Report (WSR). Follow directions on the form.
14. SITE LAYOUT
Sketch a layout of the site. Be sure to include the location of the system, hose outlets, data terminals,
external modems, circuit breakers and distances between units.
Check off the appropriate box for Start-up Complete, Start-Up Incomplete, and fill in the number for
Number of Start-Up Attempts.